Concrete Calculator
Enter your dimensions — the answer updates as you type. No submit button.
Order 1.75 yd³ — that includes the waste allowance below.
- Cubic feet
- 40.00
- 80 lb bags
- 74
- 60 lb bags
- 98
- Waste
- Ready-mix $/yd³
- Bag price $
Ready-mix: $289 · 80 lb bags: $479
How the math works
Volume in cubic yards is length × width × thickness ÷ 27. The 27 is because one cubic yard is 27 cubic feet — that is the only conversion you need.
For a 10 × 12 ft shed slab at 4 inches:
- 10 × 12 = 120 sq ft
- 120 × (4 ÷ 12) = 40 cubic feet
- 40 ÷ 27 = 1.48 cubic yards
- Add 10% waste → 1.63, round up to the nearest quarter yard → order 1.75 yd³
How much a bag covers
| Bag size | Yield (ft³) | Bags per yd³ | Covers at 4 in |
|---|---|---|---|
| 40 lb | 0.30 | 90 | 0.9 sq ft |
| 50 lb | 0.375 | 72 | 1.1 sq ft |
| 60 lb | 0.45 | 60 | 1.4 sq ft |
| 80 lb | 0.60 | 45 | 1.8 sq ft |
Yields are the manufacturers' published figures. Wet mixing adds air, so bag counts are always rounded up.
Ready-mix or bags?
The crossover is around two cubic yards — later than most people expect, because the fees matter more than the concrete.
| You need | Ready-mix, all in | 80 lb bags |
|---|---|---|
| ½ yd³ | $200–$285 | $149 |
| 1 yd³ | $285–$365 | $291 |
| 2 yd³ | $405–$480 | $582 |
| 3 yd³ | about $495 | $873 |
Bags run 45 to a cubic yard at $6.47 each, so $291 a yard every time — and a bag never sends you a fee.
Three fees to ask about before you order:
- Short-load fee. Under 1 yard it is usually $120–$200 flat; 1 to 3 yards, $75–$150. Between 3 and 5 yards, expect $15–$40 per yard under the plant's minimum.
- Minimum quantity. Plenty of plants bill a 3-yard minimum whether the truck pours it or not.
- Distance. Past 20 miles, budget roughly $9.50 a mile.
For that 10 × 12 ft slab (order 1.75 yd³): ready-mix is about $289 of concrete plus a $75–$150 short load, so $364–$439 all in. Seventy-four bags come to $479 and cost you a Saturday. That is the real decision — call two plants and ask for the all-in price, not the per-yard price.
Prices checked November 2026 and refreshed every quarter.
Pick the right thickness
| Pour | Thickness | Typical mix |
|---|---|---|
| Patio, walkway | 4 in | 3,500 psi |
| Shed slab | 4 in | 3,000 psi |
| Driveway (cars) | 5 in | 4,000 psi |
| Driveway (trucks/RV) | 6 in | 4,000 psi, air-entrained |
| Footing | 8–12 in | 2,500 psi |
Five ways people run short
- Forgetting waste. Spills, an uneven subgrade and bowed forms eat 5–10%. Always round up, never down.
- Measuring the subgrade, not the form. The slab is as thick as the form is tall. Check it in four places.
- Not accounting for a thickened edge. A slab with a turned-down edge can add 20%.
- Ordering on a Friday afternoon. Plants run out, and a second truck is another short-load fee.
- Adding water to stretch the mix. Every extra gallon takes a few hundred psi out of the mix. If it is short, it is short.
Questions people actually ask
How many 80 lb bags for a 10×10 slab?
At 4 inches: 100 sq ft × 0.333 ft = 33.3 ft³ = 1.23 yd³. Divide by 0.60 ft³ per bag → 56 bags, and buy 62 with a 10% cushion. At 6 inches the same 100 sq ft takes 92 bags with that cushion.
How much does a yard of concrete cover?
81 sq ft at 4 inches, 108 sq ft at 3 inches, 54 sq ft at 6 inches. A cubic yard weighs about 4,050 lb, or just over two US tons.
How much does concrete cost per cubic yard?
$140–$190 delivered for ready-mix in 2026, with a national middle near $165. The bagged equivalent is about $291 a yard at $6.47 an 80 lb bag — which is why bags are for fence posts and small pads, not slabs.
How long before I can walk on it?
24–48 hours to walk, about 7 days before a car, 28 days for full design strength. Cold weather (below 40°F) and hot weather (above 90°F) both stretch those numbers.
Do I need rebar?
Yes for driveways and any slab over 4 inches: #4 rebar at 12 in on center, or 6×6 W2.9×W2.9 mesh for patios and walkways. Keep it in the middle third of the slab, not on the ground.
Can I mix it in a wheelbarrow?
One or two 80 lb bags per batch. A standard contractor wheelbarrow holds about 6 ft³, and a batch that size is already hard to turn over by hand. Past about 10 bags, rent a mixer.
Why is my slab cracking at the corners?
Usually no control joints. Cut them within 6–12 hours of finishing, at a depth of a quarter of the slab thickness, every 8–10 ft in both directions.